Launch of work in the Kergoat Ar Lez district: redevelopment of the streets Chateaubriand, Jean-Merrien and Louis-Pasteur

IN BRIEF

  • Start of work : September 16, 2024
  • Objective : Secure travel and pedestrian and cycling
  • mobility Duration of network works
  • : September 16 – December 16, 2024 Streets concerned
  • : Chateaubriand, Jean-Merrien and Louis-Pasteur Network renewal
  • : drinking water, wastewater, rainwater Amount of work
  • : €684,000 incl. tax Road works
  • : January 1 – June 30, 2025 Traffic changes
  • : one-way, two-way cycling Creation of accessible sidewalks and permeable parking spaces
  • Amount of road works : €415,000 incl. tax

The Kergoat Ar Lez district is preparing to undergo major transformations with the launch of the redevelopment works of the Chateaubriand, Jean-Merrien and Louis-Pasteur streets. After a series of consultations that involved residents, shopkeepers and schools, this initiative aims to improve travel safety for both pedestrians and cyclists. The first phases of this work will begin soon, marking the start of an ambitious project to revitalize and secure this important sector.

The city of Quimper is preparing for a major development project in the Kergoat Ar Lezdistrict, aimed at transforming the Chateaubriand, Jean-Merrien and Louis-Pasteurstreets. Following several years of consultation with the various stakeholders in the district, this work will begin soon to improve safety and facilitate travel for pedestrians and cyclists. This project will take place in several phases, with interventions on the networks before focusing on the roads. Work details

The first phase of the work will focus on the rehabilitation of the water networks. Scheduled from

September 16 to December 16, 2024 , it will affect Chateaubriand, Jean-Merrien and Louis-Pasteur streets. These interventions will include:Drinking water supply

  • : renewal of the network and connections. Wastewater
  • : renewal of the existing network. Rainwater
  • : modernization of the network for better management of rainwater. During this period, traffic will be disrupted, the road will be blocked, but access will still be maintained for local residents in order to minimize inconvenience.

Road development

The second phase, which will take place from

January 1 to June 30, 2025 , will focus on the redevelopment of the roads themselves in the Kergoat Ar Lez district. This work will aim to:Rue Chateaubriand

Maintain the

  • double direction of traffic .Create a
  • accessible sidewalk for pedestrians. Proceed with the
  • road repair .Delete them
  • side gutters .Implement
  • permeable parking spaces .Rue Jean-Merrien

Implementation

  • One Way for motorized vehicles with the creation of a two-way cycle .Establish a
  • accessible sidewalk .Carry out the
  • road repair .Remove the
  • side gutters .Rue Louis-Pasteur

Implementation

  • One Way for motorized vehicles and introduction of a two-way cycle .Creation of
  • retarder plates to improve security. Installing a
  • accessible and protected sidewalk by street furniture. Realization of the
  • road repair .Removal of
  • side gutters .Maintaining the
  • bilateral parking .Establishment of
  • permeable parking spaces .Amount of work

The total cost of this work amounts to

€684,000 including tax for the network renewal phase, and €415,000 including tax for road improvements. This ambitious project demonstrates the city’s commitment to better sustainable mobility and an improved living environment for all residents. Impact on residents’ daily lives

The work, although necessary for the development and safety of the neighborhood, will require daily adjustments for residents and road users. However, these developments aim to establish a more welcoming, secure and accessible environment for pedestrians and cyclists, which is fundamental in a rapidly evolving urban context.

To find out more about the details and progress of this work, consult the news offered by Quimper town hall on the official website, as well as additional resources concerning development projects in the area.

community of communes Châteaubriant .FAQ on the redevelopment of the Kergoat Ar Lez district

What work will be carried out in the Kergoat Ar Lez district?

Redevelopment work on Chateaubriand, Jean-Merrien and Louis-Pasteur streets is planned to make pedestrian and bicycle travel safer. When does the work start?

Network work will begin on September 16, 2024 and end on December 16, 2024. What types of networks will be renewed?

The work will include the renewal of the drinking water supply, wastewater and rainwater networks. What changes will be made to the streets?

There will be changes such as the creation of accessible sidewalks, road repairs and the provision of permeable parking spaces. What is the total cost of the work?

The total amount of work amounts to €684,000 including tax for the first phase dedicated to the networks, and €415,000 including tax for the road works. When will the road work take place?

The road work will be carried out from January 1 to June 30, 2025. How will traffic be regulated during the work?

The road will be blocked, but access will be maintained for local residents to minimize inconvenience.